PTC film heating finished product installation video
Hello, this is KPF.
2.8m x 2.75m of the finished products on the PTC ship that can be easily installed by one person
I'll show you how to work
(The size of the room to be built is 3m wide x 3m long)
First, I will show you the process of making our KPF finished product.
You can trust and entrust the work to film experts.
Film heating is cut to the size of the film ordered.
Cut the wire to be attached to the film finished product according to the film heating size.
(I cut it generously for ease of installation)
Connect the flat top terminal to the copper foil part of the film heating
Cover the electric wire and peel it off neatly
Put the uneven part into the face terminal and fix it with a dedicated presser.
(Be careful not to crumple the film when fixing it with a presser)
After fixing the face-up terminal, attach butyl tape to the front and back of the face-up terminal to prevent electricity from flowing.
Tape the front and back of the butyl tape with the KPF phone number written on it.
(Call us at 1800-6384 if there is a problem with the product or if you have any questions)
After electrical finishing with butyl tape on the back of the film, double-finish with KPF tape.
This is the film production process
Additional materials required for the construction of the finished product are packed in the same way.
(OPP tape, molding, installation manual)
When packing, the film insulation material is also rolled up and wrapped in plastic and sent to the customer.
After receiving the finished film heating product you ordered
I will show you how to build
The room size is 3m x 3m with black tape.
I will show you how to construct it in this space.
1. Clean the floor thoroughly before construction
2. After cleaning, spread film-only insulation over the entire room.
3. After laying the insulation material, fix the insulation material with the included OPP tape so that the insulation material does not move.
4. Lay the finished film heating product over the insulation material.
(Push out the film one by one and spread it out)
5. Like the insulation, fix it with OPP tape so that the film heating does not move.
(Fix it with OPP tape so that it does not move between the palm and the film)
6. Loosen the regulator attached to the film heating and plug it into an outlet to check whether the regulator turns on or if the film heats up normally.
7. After checking, arrange the wires of the finished product of film heating and fix it with OPP tape.
8. Attach the dry sensor connected to the regulator to the black part of the film heating.
9. With the additionally purchased plywood board, cover the discharge body with the film
(It is normal for there to be some gaps between the plywood boards)
10. Fix the plywood board so that it does not move with OPP tape.
This concludes the construction method of the finished film heating product.
Thank you
Hello, this is KPF.
2.8m x 2.75m of the finished products on the PTC ship that can be easily installed by one person
I'll show you how to work
(The size of the room to be built is 3m wide x 3m long)
First, I will show you the process of making our KPF finished product.
You can trust and entrust the work to film experts.
Film heating is cut to the size of the film ordered.
Cut the wire to be attached to the film finished product according to the film heating size.
(I cut it generously for ease of installation)
Connect the flat top terminal to the copper foil part of the film heating
Cover the electric wire and peel it off neatly
Put the uneven part into the face terminal and fix it with a dedicated presser.
(Be careful not to crumple the film when fixing it with a presser)
After fixing the face-up terminal, attach butyl tape to the front and back of the face-up terminal to prevent electricity from flowing.
Tape the front and back of the butyl tape with the KPF phone number written on it.
(Call us at 1800-6384 if there is a problem with the product or if you have any questions)
After electrical finishing with butyl tape on the back of the film, double-finish with KPF tape.
This is the film production process
Additional materials required for the construction of the finished product are packed in the same way.
(OPP tape, molding, installation manual)
When packing, the film insulation material is also rolled up and wrapped in plastic and sent to the customer.
After receiving the finished film heating product you ordered
I will show you how to build
The room size is 3m x 3m with black tape.
I will show you how to construct it in this space.
1. Clean the floor thoroughly before construction
2. After cleaning, spread film-only insulation over the entire room.
3. After laying the insulation material, fix the insulation material with the included OPP tape so that the insulation material does not move.
4. Lay the finished film heating product over the insulation material.
(Push out the film one by one and spread it out)
5. Like the insulation, fix it with OPP tape so that the film heating does not move.
(Fix it with OPP tape so that it does not move between the palm and the film)
6. Loosen the regulator attached to the film heating and plug it into an outlet to check whether the regulator turns on or if the film heats up normally.
7. After checking, arrange the wires of the finished product of film heating and fix it with OPP tape.
8. Attach the dry sensor connected to the regulator to the black part of the film heating.
9. With the additionally purchased plywood board, cover the discharge body with the film
(It is normal for there to be some gaps between the plywood boards)
10. Fix the plywood board so that it does not move with OPP tape.
This concludes the construction method of the finished film heating product.
Thank you
PTC film heating semi-finished product construction video
Hello, this is KPF.
I will show you how to construct a semi-finished product on a PTC ship that can be easily installed by one person.
First, I will show you our KPF semi-finished product production process.
You can trust and entrust the work to film experts.
Film heating is cut to the size of the film ordered.
Cut the wire 10cm
Cover the wires and peel off both sides neatly
Connect the face terminal to the copper foil part of the film heating in front of the covered wire
Put the uneven part into the face terminal and fix it with a dedicated presser.
(Be careful not to crumple the film when fixing it with a presser)
Insert the sleeve connecting the wire to the rest of the wire and fix it.
(Compress the sleeve with a dedicated crimping tool)
After fixing the face-up terminal, attach butyl tape to the front and back of the face-up terminal to prevent electricity from flowing.
Tape the front and back of the butyl tape with the KPF phone number written on it.
(Call us at 1800-6384 if there is a problem with the product or if you have any questions)
After electrical finishing with butyl tape on the back of the film, double-finish with KPF tape.
This is the film production process
Additional materials required for the construction of the finished product are packed in the same way.
(OPP tape, molding, installation manual)
When packing, the film insulation material is also rolled up and wrapped in plastic and sent to the customer.
After receiving the finished film heating product you ordered
I will show you how to build
The room size is 3m x 3m with black tape.
I will show you how to construct it in this space.
1. Clean the floor thoroughly before construction
2. After cleaning, spread film-only insulation over the entire room.
3. After laying the insulation material, fix the insulation material with the included OPP tape so that the insulation material does not move.
4. Lay the semi-finished film heating on the insulation
(Push out the film one by one and spread it out)
5. Like the insulation, fix it with OPP tape so that the film heating does not move.
(Fix it with OPP tape so that it does not move between the palm and the film)
6. Loosen the additionally purchased electric wire and cover the end of the electric wire, twist the electric wire into the sleeve, and press it with a crimping machine.
7. From the second film, cut the sleeve wire connected to the first film and the wire length of the second film, cover the wire, twist the two wires and connect them to the sleeve
(Connect all remaining wires)
8. Loosen the attached regulator and plug it into an outlet to check whether the regulator turns on or if the film heats up normally.
9. After checking, wrap the sleeve with electrical tape or butyl tape to prevent electricity from flowing.
10. After finishing, arrange the wires of the finished product of film heating and fix it with OPP tape.
11. Attach the dry sensor connected to the controller to the black part of the film heating.
12. With the additionally purchased plywood board, cover the discharge body with the film
(It is normal for there to be some gaps between the plywood boards)
13. Fix the plywood board without moving with OPP tape.
This concludes the construction method of the finished film heating product.
Thank you
Hello, this is KPF.
I will show you how to construct a semi-finished product on a PTC ship that can be easily installed by one person.
First, I will show you our KPF semi-finished product production process.
You can trust and entrust the work to film experts.
Film heating is cut to the size of the film ordered.
Cut the wire 10cm
Cover the wires and peel off both sides neatly
Connect the face terminal to the copper foil part of the film heating in front of the covered wire
Put the uneven part into the face terminal and fix it with a dedicated presser.
(Be careful not to crumple the film when fixing it with a presser)
Insert the sleeve connecting the wire to the rest of the wire and fix it.
(Compress the sleeve with a dedicated crimping tool)
After fixing the face-up terminal, attach butyl tape to the front and back of the face-up terminal to prevent electricity from flowing.
Tape the front and back of the butyl tape with the KPF phone number written on it.
(Call us at 1800-6384 if there is a problem with the product or if you have any questions)
After electrical finishing with butyl tape on the back of the film, double-finish with KPF tape.
This is the film production process
Additional materials required for the construction of the finished product are packed in the same way.
(OPP tape, molding, installation manual)
When packing, the film insulation material is also rolled up and wrapped in plastic and sent to the customer.
After receiving the finished film heating product you ordered
I will show you how to build
The room size is 3m x 3m with black tape.
I will show you how to construct it in this space.
1. Clean the floor thoroughly before construction
2. After cleaning, spread film-only insulation over the entire room.
3. After laying the insulation material, fix the insulation material with the included OPP tape so that the insulation material does not move.
4. Lay the semi-finished film heating on the insulation
(Push out the film one by one and spread it out)
5. Like the insulation, fix it with OPP tape so that the film heating does not move.
(Fix it with OPP tape so that it does not move between the palm and the film)
6. Loosen the additionally purchased electric wire and cover the end of the electric wire, twist the electric wire into the sleeve, and press it with a crimping machine.
7. From the second film, cut the sleeve wire connected to the first film and the wire length of the second film, cover the wire, twist the two wires and connect them to the sleeve
(Connect all remaining wires)
8. Loosen the attached regulator and plug it into an outlet to check whether the regulator turns on or if the film heats up normally.
9. After checking, wrap the sleeve with electrical tape or butyl tape to prevent electricity from flowing.
10. After finishing, arrange the wires of the finished product of film heating and fix it with OPP tape.
11. Attach the dry sensor connected to the controller to the black part of the film heating.
12. With the additionally purchased plywood board, cover the discharge body with the film
(It is normal for there to be some gaps between the plywood boards)
13. Fix the plywood board without moving with OPP tape.
This concludes the construction method of the finished film heating product.
Thank you